SH 119 Emergency Flood Repairs Modified Design-Build

Boulder, CO

This emergency project was completed as an immediate emergency response to remediate flood damage to SH 119 due to of Boulder Creek. The project consisted of 20,000 cubic yards of excavation and embankment, over 500 tons of hot mix asphalt patching, more than 4,000 cubic yards of riprap bank fortification, cleaning and repair of culverts, removal of mudslide debris, and other corrective improvements. The project was completed 2 months ahead of schedule allowing CDOT to reopen the road sooner than initially planned and well in advance of other flood remediation projects